Tuesday, 13 October 2026
Englishहिन्दीMarathi
City News Mumbai
City News Mumbai
HomeE-PaperVideosNationalMumbaiPoliticsSportsHealthTechnologyCrimeHistory
TopNationalMumbaiPoliticsSportsHealthTechnologyCrimeHistory

City News Mumbai

Every News from Mumbai, First.

Categories

  • Local
  • National
  • Politics
  • Business
  • Technology
  • Sports
  • Health
  • Education

Quick Links

  • Home
  • E-Paper
  • Videos
  • Picture of the Day
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms of Service

Newsroom

  • Editorial Policy
  • Corrections & Complaints
  • Advertise With Us
  • Newsroom Contact

Languages

  • English
  • हिन्दी (Hindi)
  • मराठी (Marathi)

Follow Us

Email: citynewsmumbai@gmail.com

Phone: 9869128483

© 2026 City News Mumbai. All rights reserved

Designed and Developed byZeloiteZeloite
"C-Link" gets an extension.......; the public bears the cost burden........? Original deadline 2024; now directly 2028....!
  1. Home
  2. Mumbai
Mumbai

"C-Link" gets an extension.......; the public bears the cost burden........? Original deadline 2024; now directly 2028....!

City News Mumbai•29 August 2026 at 04:04 pm•15 views•1 min read

Information-right activist Anil Galgali questions MSRDC Who will bear the cost of the four-year delay?

Mumbai, dated 29 (Anant Nalawe) – The Versova‑Bandra sea link project, being built to speed up Mumbai’s traffic, has been granted a total extension of 1,421 days; however, where is the account of whether a penalty has been imposed for the contractor’s delay...? This direct question was raised by Right to Information activist Anil Galgali.

The ambitious project, which began on 24 June 2019, originally had a completion date of 21 June 2024. After granting extensions in four stages, that date has now moved directly to 17 May 2028. Hence the political and administrative question arises: is the extension a concession to the project or to the contractor…?

According to information obtained from MSRDC under RTI, the first extension of 250 days was granted because land for the casting yard was not available. Subsequently, an additional 180 days were added to account for disruptions caused by COVID‑19. Further, a total of 483 days was approved due to restructuring within the EPC contractor’s joint venture, and another 508 days was sanctioned on the basis of changes in the scope of work and additional tasks. Thus, the sum of the four extensions amounts to 1,421 days…!

‘Deadline’ pushed four years ahead
Share:

More from Mumbai

Mumbai

12 Oct 2026
Congress surrounds Chief Minister Devendra Fadnavis from SIAR...
Mumbai

Congress surrounds Chief Minister Devendra Fadnavis from SIAR...

10 Oct 2026
मादक पदार्थों के अपराधों की अब होगी “फास्ट ट्रैक” सुनवाई!
Mumbai

मादक पदार्थों के अपराधों की अब होगी “फास्ट ट्रैक” सुनवाई!

7 Oct 2026
Organizing “Vikasit Bharat Sankalp Sabha” and “Seva Jyoti Yatra” under the Service Resolution Campaign.
Mumbai

Organizing “Vikasit Bharat Sankalp Sabha” and “Seva Jyoti Yatra” under the Service Resolution Campaign.

7 Oct 2026
Pandit Dindayal Upadhyay proposes changes to allowances in the Self-Employment Scheme.
Mumbai

Pandit Dindayal Upadhyay proposes changes to allowances in the Self-Employment Scheme.

6 Oct 2026
Even the district scheme funds are being directed towards drought relief...! Administrative approval deadline extended until 30 November...; priority given to water conservation, agriculture, health and education projects.
Mumbai

Even the district scheme funds are being directed towards drought relief...! Administrative approval deadline extended until 30 November...; priority given to water conservation, agriculture, health and education projects.

6 Oct 2026