Saturday, 29 August 2026
Englishहिन्दीMarathi
City News Mumbai
City News Mumbai
HomeE-PaperVideosNationalMumbaiPoliticsSportsHealthTechnology
TopNationalMumbaiPoliticsSportsHealthTechnology

City News Mumbai

Every News from Mumbai, First.

Categories

  • Local
  • National
  • Politics
  • Business
  • Technology
  • Sports
  • Health
  • Education

Quick Links

  • Home
  • E-Paper
  • Videos
  • Picture of the Day
  • About Us
  • Contact Us
  • Privacy Policy
  • Terms of Service

Newsroom

  • Editorial Policy
  • Corrections & Complaints
  • Advertise With Us
  • Newsroom Contact

Languages

  • English
  • हिन्दी (Hindi)
  • मराठी (Marathi)

Follow Us

Email: citynewsmumbai@gmail.com

Phone: 9869128483

© 2026 City News Mumbai. All rights reserved

Designed and Developed byZeloiteZeloite
"C-Link" gets an extension.......; the public bears the cost burden........? Original deadline 2024; now directly 2028....!
  1. Home
  2. Mumbai
Mumbai

"C-Link" gets an extension.......; the public bears the cost burden........? Original deadline 2024; now directly 2028....!

City News Mumbai•29 August 2026 at 04:04 pm•7 views•1 min read

Information-right activist Anil Galgali questions MSRDC Who will bear the cost of the four-year delay?

Mumbai, dated 29 (Anant Nalawe) – The Versova‑Bandra sea link project, being built to speed up Mumbai’s traffic, has been granted a total extension of 1,421 days; however, where is the account of whether a penalty has been imposed for the contractor’s delay...? This direct question was raised by Right to Information activist Anil Galgali.

The ambitious project, which began on 24 June 2019, originally had a completion date of 21 June 2024. After granting extensions in four stages, that date has now moved directly to 17 May 2028. Hence the political and administrative question arises: is the extension a concession to the project or to the contractor…?

According to information obtained from MSRDC under RTI, the first extension of 250 days was granted because land for the casting yard was not available. Subsequently, an additional 180 days were added to account for disruptions caused by COVID‑19. Further, a total of 483 days was approved due to restructuring within the EPC contractor’s joint venture, and another 508 days was sanctioned on the basis of changes in the scope of work and additional tasks. Thus, the sum of the four extensions amounts to 1,421 days…!

‘Deadline’ pushed four years ahead
Share:

More from Mumbai

"Political birth" by whose grace.....? The Tatkare‑Dalvi clash erupts; "We wouldn't have withdrawn the form"
Mumbai

"Political birth" by whose grace.....? The Tatkare‑Dalvi clash erupts; "We wouldn't have withdrawn the form"

29 Aug 2026
Free health, eye and cancer screening camp on Muzhafar Hussain's birthday; wheelchairs distributed to 40 persons with disabilities
Mumbai

Free health, eye and cancer screening camp on Muzhafar Hussain's birthday; wheelchairs distributed to 40 persons with disabilities

26 Aug 2026
Controversy over Gujarati welcome for Mayor Dimples Mehta, with the Marathi Integration Committee and MNS voicing objections.
Mumbai

Controversy over Gujarati welcome for Mayor Dimples Mehta, with the Marathi Integration Committee and MNS voicing objections.

26 Aug 2026
Chief Minister set to soon hammer the “moldy” chairs in the ministry…!
Mumbai

Chief Minister set to soon hammer the “moldy” chairs in the ministry…!

25 Aug 2026
Torrent Power employees celebrated Raksha Bandhan at old‑age homes, bringing smiles to the elders’ faces.
Mumbai

Torrent Power employees celebrated Raksha Bandhan at old‑age homes, bringing smiles to the elders’ faces.

25 Aug 2026
Kalyan Naka echoed with the slogan “Go to the pits,” featuring a unique performance by Rakampa with Manvi Ganpati.
Mumbai

Kalyan Naka echoed with the slogan “Go to the pits,” featuring a unique performance by Rakampa with Manvi Ganpati.

25 Aug 2026